Where examination of the underlying transaction is necessary to establish fraud under an independent guarantee, courts shall adhere to the principle of limitation and necessity. A beneficiary’s breach under the underlying contract does not impair its right to present documents and make a demand for payment pursuant to the independent‑guarantee terms. Even if fraud exists under an independent guarantee, people’s courts shall not order suspension of payment under an independent counter‑guarantee where payment under the primary independent guarantee has already been made in good faith.

Case: Breach by the Beneficiary under the Underlying Contract Does Not Bar Its Demand for Payment under an Independent Guarantee
Where examination of the underlying transaction is necessary to establish fraud under an independent guarantee, courts shall adhere to the principle of limitation and necessity. A beneficiary’s breach under the underlying contract does not impair its right to present documents and make a demand for payment pursuant to the independent‑guarantee terms. Even if fraud exists under an independent guarantee, people’s courts shall not order suspension of payment under an independent counter‑guarantee where payment under the primary independent guarantee has already been made in good faith.
Key Adjudicative Points
- Where examination of the underlying transaction is required to determine fraud under an independent guarantee, the principle of limitation and necessity shall apply. The scope of review is confined to whether the beneficiary knew that its counterparty under the underlying contract had committed no breach thereunder, or whether the beneficiary knew it possessed no valid claim for payment.
- A beneficiary’s breach of obligations under the underlying contract shall not affect its right to submit documents and demand payment under the independent guarantee.
- When assessing fraud under an independent counter‑guarantee: even if fraud occurs under the primary independent guarantee, people’s courts shall not order suspension of payment under the independent counter‑guarantee if payment under the primary independent guarantee has been effected in good faith.
Basic Facts
Adjudicative Outcome
- First Instance (Hefei Intermediate People’s Court, 9 April 2014), Civil Judgment (2012) He Min Si Chu Zi No. 00005:
- Oriental Real Estate’s demand under Performance Guarantee G051225 constituted guarantee fraud;
- CCB Anhui Branch shall cease paying USD 2,008,000 under Counter‑Guarantee 34147020000289 to Banco de Costa Rica;
- Other claims of Anhui FECC Group were dismissed.
- Second Instance (Anhui High People’s Court, 19 March 2015), Civil Judgment (2014) Wan Min Er Zhong Zi No. 00389: Appeal dismissed; original judgment affirmed.
- Retrial (Supreme People’s Court, 14 December 2017), Civil Judgment (2017) Zui Gao Fa Min Zai No. 134:
- Set aside the civil judgments of Anhui High People’s Court (2014) Wan Min Er Zhong Zi No. 00389 and Hefei Intermediate People’s Court (2012) He Min Si Chu Zi No. 00005;
- Dismiss all claims filed by Anhui FECC Group.